Logframe template and how to use it (free download)
A logframe is a matrix that links a programme's goal, outcomes, outputs and activities to indicators, evidence sources and assumptions. Download the free template, build it top-down from the goal, then test the logic bottom-up.
Milestra team · 27 October 2026 · 7 min read
What a logframe is
A logframe (logical framework) is a one-page summary of how a programme is supposed to work and how you will prove it. Most institutional funders ask for one, and it becomes the backbone of your monitoring and reporting for the life of the grant.
The classic matrix has four rows and four columns:
| Narrative summary | Indicators | Means of verification | Assumptions | |
|---|---|---|---|---|
| Goal (impact) | The long-term change you contribute to | How you would see it | Where the data comes from | |
| Outcome(s) | The change the programme is accountable for | Measurable signs of that change | Sources | Conditions needed for the outcome to lead to the goal |
| Outputs | What the programme delivers | Counts and quality measures | Sources | Conditions needed for outputs to lead to outcomes |
| Activities | What you do | Often inputs or budget | Sources | Conditions needed for activities to produce outputs |
Funders use different words for the same levels. "Impact", "goal" and "overall objective" usually mean the top row; "outcome", "purpose" and "specific objective" the second. Always use your funder's terms in the version you submit.
Download the free logframe template
Get the free logframe template (Excel). It opens in Excel, Google Sheets and LibreOffice, and has three sheets:
- Logframe: the four-by-four matrix, with a completed example from an education programme that you can overwrite.
- Indicators: one row per indicator with level, definition, unit, baseline, target, actual, frequency, source and owner. The percentage of target is calculated for you, from the baseline.
- How to use: the steps below, in short.
Enter your email on the template page and we send it straight to your inbox. The rest of this guide explains how to fill it in.
Step 1: Agree the problem and the goal
Start with a clear problem statement, ideally backed by data you already have. For example: "Only 38% of Grade 3 learners in the programme schools read at the expected level."
The goal is the long-term change you contribute to: "More children complete primary education with strong foundational skills." Keep it high-level. You will not achieve it alone, and that is fine.
Step 2: Define the outcome
The outcome is the change your programme is accountable for by the end. One to three outcomes is typical.
Outcome: Learners in 210 schools across four countries read at the expected level for their grade (38% → 55%).
If you need more than three outcomes, you probably have more than one programme, or you are describing outputs.
Step 3: List the outputs that will cause the outcome
Outputs are what you deliver. Ask: what must exist for the outcome to happen?
- Output 1: Teachers trained and coached in structured reading methods
- Output 2: Schools supplied with levelled reading materials
- Output 3: School leaders using termly reading data to plan
Step 4: Plan the activities under each output
Activities are the work. Under Output 1: design the course, train 40 trainers, run training in four countries, provide monthly in-class coaching. Keep the logframe to the main activities; the detailed work plan sits elsewhere.
Step 5: Add indicators for each level
Each indicator needs a unit, baseline, target and frequency. Use the Indicators sheet in the template.
| Level | Indicator | Baseline | Target | Frequency |
|---|---|---|---|---|
| Outcome | % of Grade 3 learners reading at the expected level | 38% | 55% | Each term |
| Output 1 | Teachers completing the full course | 0 | 600 | Quarterly |
| Output 1 | Teachers using the method in 3+ lessons a week | 20% | 75% | Termly observation |
| Output 2 | Schools with a full set of levelled readers | 30 | 210 | Quarterly |
| Output 3 | Schools submitting reading data on time | 120 | 200 | Each term |
Two or three indicators per level is enough. Every indicator costs time to collect, so each one should earn its place.
Step 6: Fill in the means of verification
For each indicator, name the evidence: reading assessment results, training attendance registers, classroom observation forms, delivery notes, school data submissions. If you cannot name a source, the indicator is not ready.
Be specific. "Programme records" is not a means of verification. "Signed training attendance registers, held by the country office" is.
Step 7: Write the assumptions
Assumptions are conditions outside your control that must hold for each level to lead to the next.
- Activities → Outputs: trained trainers stay in post for the programme
- Outputs → Outcome: teachers have enough class time for daily reading
- Outcome → Goal: learners stay in school through upper primary
Then test the logic bottom-up: if we do these activities and the assumptions hold, then we deliver the outputs, and so on up the matrix. If any step feels like a leap, add an output or an assumption.
Example logframes from other sectors
The same structure works for any sector. Two short extracts:
Water, sanitation and hygiene
| Level | Statement | Indicator |
|---|---|---|
| Outcome | Households in programme districts use safe water all year | % of households using an improved water source in the dry season |
| Output | Water points rehabilitated and maintained | % of water points functional at monthly check |
| Output | Water committees trained and active | # of committees with a maintenance fund and quarterly meeting record |
Maternal health
| Level | Statement | Indicator |
|---|---|---|
| Outcome | Women in programme districts receive antenatal care early | % of pregnant women with a first antenatal visit in the first trimester |
| Output | Community health workers trained and supported | # of community health workers completing training and monthly supervision |
| Output | Facilities supplied with essential antenatal supplies | % of facilities with no stock-out during the quarter |
Common logframe mistakes
- Outputs pretending to be outcomes. "600 teachers trained" is an output. The outcome is what changes because of that training.
- Too many indicators. A logframe with 40 indicators is a data collection burden that nobody will keep up.
- No baselines. Set them before activities start, or schedule a baseline study in the first quarter.
- Assumptions that are really risks you can manage. If you can do something about it, it belongs in your plan, not the assumptions column.
- A logframe nobody uses. It should drive your quarterly plans and reports, not sit in the proposal annex.
From logframe to day-to-day tracking
The logframe tells you what to measure. You still need a way to track it, assign owners, store evidence and report. A simple approach:
- Give each indicator one owner.
- Turn the indicators that matter most this quarter into key results (see OKRs for nonprofits).
- Update numbers and attach evidence as they come in, not at report time. If your data comes from mobile surveys, see how to track programme KPIs from KoboToolbox data.
- Produce the donor report straight from the same data.
When the spreadsheet starts to strain, Milestra can hold the same indicators with owners and weekly updates and produce a logframe-style donor report from them. See the reports section of the features page.
Frequently asked questions
Is a logframe the same as a results framework?
They are close cousins. A results framework is often a diagram of the results chain; a logframe adds indicators, means of verification and assumptions in a matrix.
What is the difference between a logframe and a theory of change?
A theory of change explains why change will happen, including pathways and assumptions in detail. A logframe summarises one pathway in a matrix for management and reporting. See theory of change vs logframe vs OKRs.
Can we change our logframe during the grant?
Yes, usually through a formal request to the funder. Adjust it when evidence shows the original logic or targets were wrong, and keep a record of what changed and why.
Does the template work in Google Sheets?
Yes. Upload the file to Google Drive and open it with Google Sheets. The formulas and formatting carry over.
How many indicators should a logframe have?
Two or three per level is a good rule. For a programme with one outcome and three outputs, that is roughly eight to twelve indicators in total.
Sources and further reading
- The Logical Framework (M&E Planning Series 12) · INTRAC
- Results information: indicators, baselines and targets · International Aid Transparency Initiative (IATI)
Try Milestra for free
Put this guide into practice in 10 minutes
- Goals, key results and indicators in one place
- Two-minute weekly check-ins with reminders
- Donor and board reports from live numbers
- Free for up to 5 people · 50% off for nonprofits